Warren School

PROJECT OVERVIEW:

Create 2 FA spec grass football pitches at no cost to the school.

REASON FOR UPGRADE:

As part of a land swap the school were trading 2 very poor condition pitches for arable land on condition new pitches were created.

CLIENT:

The Crown

CLIENT OBJECTIVE:

To help conclude one deal whilst at the same time adding tremendous benefit the school.

PROJECT LENGTH:

1 year from start to finish.

PROJECT SIZE:

The project covers 3 acres and involves the importation of 60,000 m3 of environmentally approved soil.

THE PLANS:

The finished project will include the following …

  • 2 FA spec grass football pitches, including 10-metre lateral drainage and sand injection. Pitches were only handed over after a thorough maintenance program to ensure they were in excellent condition at hand over. The pitches were also white lined prior to hand over.